Tuesday, March 20, 2018

Installed two more posts

Yesterday the students dug the footings for two 6" x 6" post 24" deep. Today we set the posts in the holes and leveled them. Then we poured 4500 psi concrete into the holes. A total of eight 90 LB bags of concrete went into the footings. We beat the oncoming pineapple express storm forecasted for later today.
P1 Cut the 6 x timber and placed one of the posts.
P3 Poured concrete for one of the footings and set the 2nd post.
P4 Poured concrete for the other footing.
Note: During lunch, CPP Students brought by some flats so we can continue planting.
P5 Planted seeds into some flats.
P6 Planted seeds Cilantro into flat, discussed how to make the table top for planters.